Hazard Identification and Allocation of Safety Functions
While IEC 61511 does not specify procedures, it does require that a hazard and risk assessment be performed and that protective functions that prevent the hazard be identified and allocated as appropriate to Safety Instrumented Functions.
In practice this is usually accomplished by performing a hazard assessment using HAZOP or similar techniques. Scenarios that have a high consequence are then further evaluated using LOPA or similar techniques.
The LOPA studies identify protective functions or design elements that prevent the consequences of the scenario from occurring. These functions and design elements are generally designated as Independent Protection Layers (IPLs) and may take the form of instrumented functions such as Alarms, BPCS and Interlock functions, Physical design elements or Safety Instrumented Functions.
The Traditional Way
The market has a number of Process Hazards Assessment (PHA) software available. However, these software tools are all focused on performing PHAs or associated studies such as LOPAs and are almost always stand-alone tools. The capabilities have generally met the needs of Process Safety Engineers yet have had their limitations. Some of the available packages have attempted to extend their functionality to other phases of the Safety Lifecycle, yet they still tend to fall short of being a complete Safety Lifecycle Management function due to their original PHA focus.
Problems
Stand Alone
The biggest issues with stand-alone PHA and LOPA software packages is the fact that they are “stand alone”. They are self-contained and some of them have such draconian licensing restrictions, that sharing of PHA and LOPA data is extremely limited and often limited to transfer of paper copies of reports. Licensing costs are extremely high which results in organizations restricting the number of licenses that are available. Usually, the PHA and LOPA data can only be accessed from a very limited number of computers (often only one or two within an organization), even in view mode.
Difficult to link PHA and LOPA
A second major issue is that it is difficult, if not impossible to link PHA and LOPA data for a series of PHA and LOPA studies done on the same process. The typical life cycle of PHA and LOPA studies is that initial studies are done during initial design of a process plant, and then a revalidation of those studies is done every 5 years. Within the 5-year cycle, multiple sub-studies may be done if there are any significant revisions done to the process.
HAZOP of Record
Larger projects may use the same HAZOP tools as used for the HAZOP of Record, but they are usually considered in complete isolation from the HAZOP of Record. Often new nodes are defined that are numbered quite differently than the HAZOP of Record and may not contain the same equipment. As many of these studies are done at an engineering contractor’s office, the same licenses may also not be used. Many smaller modifications may be made that do not use the formal PHA procedure but use perceived simpler methods such as checklists and what-if analysis. The simpler methods are usually resorted because of the extreme licensing limitations noted above.